St Aldhelm's Academy, Poole, is undergoing refurbishment ahead of an official opening in September this year.

Click here for the latest gallery.

The work is now at the half-way stage, with the young people attending the Academy seeing their new facilities taking shape around them.

Work begain last summer, with a demolition gallery posted in November, including TV coverage and one of the young people driving a digger.

Later the same month, work began on footings - Galleries here and here. The demolition work was completed by the end of the year.

Steelwork began began in January 2013. A new floor was added later in the month and work continued in February.